Garden Banks Gas Pipeline, LLC Overview 

  mapinfo.gif 

Ownership: 100% Enbridge Offshore (Gas Transmission) L.L.C. 

Location: Extends from Garden Banks Block 128 to South Marsh Island Block 76, where it interconnects with 4 existing interstate pipelines to move gas onshore. 

Capacity: One billion cubic feet of gas per day. 

Diameter: 30-inch 

Length: 50 miles 

Start Up: April 1997 

Fields: Transports production originating from the Auger platform in Garden Banks Block 426,  the Enchilada platform in Garden Banks Block 128, the Baldpate platform in Garden Banks Block 260, the platform in South Marsh Island (SMI192) and the Magnolia Platform in Garden Banks 783.